Mareeba, Far North QueenslandThiess
$8,500,000
Project Value
Fencing
Division
3 years
Duration
Lotus Glen Correctional Facility

Project Overview

Fencepac partnered with Thiess to design, innovate and construct prison-standard security fencing for a new extension, and an existing refurbished section, of the Lotus Glen Correctional Facility. The project comprised multiple fencing applications including high chainwire, weldmesh and razor wire fencing, visual barriers, enclosures, electric and manual gates, and dog pound fencing.

01

The Constraint

  • ▸Three-year project completed within a fully operational correctional facility — live prison environment with strict security regulations and frequent unforeseen site entry delays
  • ▸Critical 48-hour shutdown window to join old fencing to new fencing while maintaining prison security levels
  • ▸Up to 50–60 other trades on site simultaneously — program of work had to be meticulously planned and executed with safety of all workers, prison staff and inmates a top priority
  • ▸Multiple project variations requiring new design solutions to be developed quickly
02

Our Approach

How this job was delivered — the bridge from constraint to result.

  • ▸Plan the three-year program around a fully operational Lotus Glen Correctional Facility — strict security regulations, frequent site-entry delays, and up to 50–60 concurrent trades — so prison operations were never interrupted.
  • ▸Sequence the join between existing refurbished fencing and the new extension into a critical 48-hour shutdown window, holding prison security levels while the two systems were connected.
  • ▸Keep design capacity on site: when variations arrived, develop new prison-standard fencing solutions quickly rather than waiting on a remote redesign cycle.
  • ▸Deploy a 25-person Fencepac team across high chainwire, weldmesh and razor wire, visual barriers, enclosures, electric and manual gates, and dog pound fencing for both the new extension and the refurbished section.
  • ▸Use in-house innovation to find cost-saving solutions as Thiess extended the initial $3,000,000 contract to $8,500,000 — a 283% scope increase driven by performance, not a change of contractor.
03

The Outcome

  • Initial contract of $3,000,000 extended to $8,500,000 — scope increase of 283% due to performance and ability to innovate cost-saving solutions
  • Zero lost-time injuries over the entire three-year project
  • All work fully compliant with Queensland Correctional Centre standards — zero call-backs in five years since completion
  • Functioning of the prison was not interrupted during the entire three-year contract

Project Team

2p
25 people
Fencepac Team