$2.4M
Fencepac contract value
Retaining
Division
Project overview
Design and construct 1,466m² of segmental concrete crib retaining walls up to 6.0m high including site set out, preparatory and foundation excavation, installation of durable wall components designed to provide 60 years of structural integrity.
News about this job
01
The constraint
- ▸Programming around the head contractor's schedule to avoid delays to overall project completion
- ▸Coordinating foundation crew and build crew simultaneously to maintain productivity
- ▸Local coastal showers requiring planning around concrete pours and keeping access tracks open
02
Our approach
- ▸Design and construct 1,466m² of segmental concrete crib retaining walls up to 6.0m high as one package: site set-out, foundation excavation, and wall components specified for 60 years of structural integrity.
- ▸Program Fencepac work to Shadforth Civil's head-contractor schedule so retaining did not delay overall project completion.
- ▸Run foundation and build crews at the same time: footing preparation, wall build, and crib silo infill as parallel fronts under Project Manager Allan Botha and Site Foreman Jesse Goodhue.
- ▸Plan concrete pours and keep access tracks open around Redland Bay coastal showers rather than treating weather as an afterthought.
03
The outcome
- Multiple installation crews operating simultaneously: footing preparation, wall build, and crib silo infill
- Zero safety incidents across the entire project
- High quality finish with perfect alignment and levels achieved
Project team
AB
Allan Botha
Project Manager
JG
Jesse Goodhue
Site Foreman
Related case studies
- Currell Circuit, Samford Valley
Samford Valley, QLD
- Holmview Central Shopping Centre
Holmview, QLD
- Field of Dreams, Swanbank
Swanbank, QLD
Need a team that can deliver a project like this?
Talk to Fencepac about your next fencing, noise wall, or retaining wall scope. We can help with early planning, pricing, and delivery strategy.