Palm Beach to Tugun (PB2T) — Noise Walls Package
Gold Coast, QLDHead Contractor (PB2T Alliance)
$9,607,800
Project Value
Noise Walls
Division

Project Overview
Full lifecycle delivery of noise walls including design development and certification of noise wall systems, manufacture and installation of concrete panels, construction of bored pile foundations and in-situ concrete sills, and coordination with other contractors for footing works and interface zones. All works delivered in compliance with TMR specifications and stringent quality requirements.
01
The Constraint
- ▸Significant program delays — completion occurred over three years beyond the original Date for Practical Completion
- ▸Complex utility relocations, service conflicts, and design approval delays across multiple disciplines
- ▸All works undertaken adjacent to or within active motorway corridors requiring strict traffic management staging and limited work windows
- ▸Multiple contractors operating simultaneously — coordination with footing and civil works by others while working around evolving construction sequencing and design changes
02
Our Approach
How this job was delivered — the bridge from constraint to result.
- ▸Take the noise wall package as a full lifecycle: design development and certification, manufacture and installation of concrete panels, bored pile foundations, and in-situ concrete sills — so footing interfaces sat inside one accountable team.
- ▸Stage all work to TMR specifications inside or adjacent to a live Gold Coast motorway, using traffic-management staging and limited work windows rather than assuming continuous access.
- ▸Coordinate with the principal contractor and adjacent civil fronts as utility relocations, service conflicts, and design-approval delays reshaped the sequence.
- ▸Sustain construction quality, acoustic performance, and finish requirements through remobilisations and revised staging when completion ran more than three years past the original Date for Practical Completion.
- ▸Keep Project Manager James Carruthers, Site Foreman Michael Muller, and Contracts Admin Sonya Robards on the package so safety, quality, and environmental compliance held across a prolonged delivery period.
03
The Outcome
- Delivered all noise wall works in compliance with project specifications, TMR standards, and contractual requirements
- Maintained consistent construction quality across all installations, meeting both acoustic performance criteria and project finish requirements
- Worked collaboratively with the principal contractor and adjacent work fronts to manage interfaces, sequencing changes, and access constraints
- Demonstrated ability to sustain performance over a prolonged delivery period, including multiple remobilisations and revised staging
- Adapted to ongoing program changes while maintaining safety, quality, and environmental compliance across all work areas
Project Team
JC
James Carruthers
Project Manager
MM
Michael Muller
Site Foreman
SR
Sonya Robards
Contracts Admin