QR Feeder Stations and Stabling Yards
All Case Studies
Fencing

QR Feeder Stations and Stabling Yards

13 sites around BrisbaneQueensland Rail
$3,800,000
Project Value
Fencing
Division
24 months
Duration
QR Feeder Stations and Stabling Yards

Project Overview

Security fencing upgrades, vibration fence detection system, security lighting, and CCTV at 8 stabling yards and 5 feeder stations. All works delivered on a live track network with minimal service disruption. Co-designed an innovative dual-material anti-vandal barrier to address millions in annual vandalism costs.

01

The Constraint

  • ▸Site closures required 90-day advance application — missing a window meant a 3-month delay to that site's program
  • ▸All works within a live track network requiring continuous coordination with rail operations and strict possession protocols
  • ▸Vandalism costing Queensland Rail millions per year — solution needed to be both physically robust and detection-capable
02

Our Approach

How this job was delivered — the bridge from constraint to result.

  • ▸Upgrade security fencing, vibration-fence detection, security lighting, and CCTV at eight stabling yards and five feeder stations on a live Queensland Rail network, applying for site closures 90 days in advance so a missed window did not cost a three-month delay.
  • ▸Co-design a dual-material anti-vandal barrier with integrated vibration detection cable and CCTV to address vandalism costing Queensland Rail millions per year.
  • ▸Complete 90%+ of feeder-station works with no power-grid interruption, updating the program every 14 days with cash-flow projections for full transparency to Queensland Rail.
  • ▸Hold a 15-person Fencepac team to a 24-month program that finished three months ahead of schedule, under budget, and with zero lost-time injuries across all 13 sites.
03

The Outcome

  • Completed 3 months ahead of schedule and under budget
  • 90%+ feeder station works completed with no power grid interruption
  • Co-designed innovative dual-material anti-vandal barrier with integrated vibration detection cable and CCTV
  • Zero lost time injuries across all 13 sites over 24 months
  • Program updated every 14 days with cash flow projections — full transparency to Queensland Rail

Project Team

1p
15 people
Fencepac Team

Need a team that can deliver a project like this?

Talk to Fencepac about your next fencing, Noise Wall, or retaining wall scope. We can help with early planning, pricing, and delivery strategy.